Concrete Inspection and Test Plan template

Slabs, footings, formwork and steel reinforcement are the classic hold point jobs: once the concrete is poured, nobody can see the steel again.

Slab and footing pour

Excavation to cured slab · 10 checkpoints · 2 hold, 1 witness

  1. 1
    Drawings, engineer details and permits checked
    Footing sizes, slab thickness, mesh
    Review
  2. 2
    Excavation depth and bearing checked
    Before any steel is placed. Engineer or inspector if required
    Hold point
  3. 3
    Compacted fill and moisture barrier
    Film lapped and taped, no tears
    Review
  4. 4
    Reinforcement placed and inspected
    Bar size, spacing, cover, chairs, laps - before pour
    Hold point
  5. 5
    Formwork and edges set to level
    Levels and dimensions checked
    Review
  6. 6
    Concrete delivery docket checked
    Grade, slump and time on the docket
    Witness point
  7. 7
    Slump test or cylinders taken
    Test results recorded
    Review
  8. 8
    Pour, compaction and finish
    Vibrated, finished, no cold joints
    Review
  9. 9
    Curing started
    Cured, sprayed or covered as specified
    Review
  10. 10
    Final level and finish check
    Cracks, level, surface
    Review

Formwork

Formwork before and after the pour · 6 checkpoints · 1 hold, 0 witness

  1. 1
    Formwork drawings checked
    Dimensions and heights
    Review
  2. 2
    Formwork set out and level
    Line, level and plumb
    Review
  3. 3
    Bracing and props secure
    Props and ties correct and tight
    Review
  4. 4
    Formwork inspected before pour
    Clean, oiled, tight joints
    Hold point
  5. 5
    Stripping time respected
    Checked against curing time
    Review
  6. 6
    Finished surface check
    Honeycombing, defects, tolerance
    Review

Steel reinforcement (rebar)

Bar placement and cover · 5 checkpoints · 1 hold, 0 witness

  1. 1
    Bar schedule and drawings checked
    Size, number, shape
    Review
  2. 2
    Steel delivered and stored clean
    Tags, grade, no heavy rust
    Review
  3. 3
    Bars placed to spacing
    Spacing and laps measured
    Review
  4. 4
    Cover and chairs checked
    Concrete cover to drawings
    Review
  5. 5
    Inspection before pour
    Engineer or inspector sign-off
    Hold point

Run it in OzHub

Take a photo at each checkpoint inside the app. OzHub records the time from our server and the place from the phone, keeps a fingerprint of the photo, sends hold points to your manager, and gives your client a link to approve. Read more on the ITP app page.

General information only. Follow your project specification, engineer, certifier and the relevant Australian Standards. See the disclaimer.

Questions

What is an ITP for concrete work?

An Inspection and Test Plan lists the checks, tests and sign-offs needed on concrete work, in order. Each line is a checkpoint: a hold point (work stops until approved), a witness point (the client may attend) or a review check.

Which concrete checkpoints are hold points?

Hold points in this template: Excavation depth and bearing checked; Reinforcement placed and inspected; Formwork inspected before pour; Inspection before pour.

Can I edit this template?

Yes. In OzHub you can copy a template, add or remove checkpoints and change which ones are hold or witness points. Your project specification and engineer come first.

Does my client need the app?

No. They get a private link by email, see the checkpoints and photos, type their name and approve or reject. No app or login.