OzHub
ITP template

Plumbing Inspection and Test Plan template

Pressure tests and drainage tests need to be witnessed before walls are lined. Record the gauge reading and the time.

Rough-in and pressure test

Pipes before linings (AS/NZS 3500) · 7 checkpoints · 1 hold, 2 witness

  1. 1
    Plans and fixture positions checked
    Review
  2. 2
    Water supply pipes installed
    Material, clips and falls
    Review
  3. 3
    Drainage pipes laid to fall
    Fall measured
    Review
  4. 4
    Pressure test of supply
    Gauge reading and time on photo
    Witness point
  5. 5
    Water test of drainage
    Standing water held
    Witness point
  6. 6
    Inspection before closing walls
    Plumbing inspector or manager
    Hold point
  7. 7
    Compliance certificate lodged
    Licence and certificate number
    Review

Gas fitting

Install, leak test and commission · 6 checkpoints · 1 hold, 1 witness

  1. 1
    Gas appliances and sizing checked
    Review
  2. 2
    Pipework installed and supported
    Review
  3. 3
    Pressure and leak test
    Gauge photo with time
    Witness point
  4. 4
    Inspection or certificate before connecting
    Hold point
  5. 5
    Appliances connected and flue checked
    Review
  6. 6
    Commissioning and handover to client
    Review

Run it in OzHub

Take a photo at each checkpoint inside the app. OzHub records the time from our server and the place from the phone, keeps a fingerprint of the photo, sends hold points to your manager, and gives your client a link to approve. Read more on the ITP app page.

General information only. Follow your project specification, engineer, certifier and the relevant Australian Standards. See the disclaimer.

Questions

What is an ITP for plumbing work?

An Inspection and Test Plan lists the checks, tests and sign-offs needed on plumbing work, in order. Each line is a checkpoint: a hold point (work stops until approved), a witness point (the client may attend) or a review check.

Which plumbing checkpoints are hold points?

Hold points in this template: Inspection before closing walls; Inspection or certificate before connecting.

Can I edit this template?

Yes. In OzHub you can copy a template, add or remove checkpoints and change which ones are hold or witness points. Your project specification and engineer come first.

Does my client need the app?

No. They get a private link by email, see the checkpoints and photos, type their name and approve or reject. No app or login.